Building a fourplex or sixplex in Toronto.

Where Toronto allows four, five and six units, what a multiplex costs to build, how the numbers work at a 6% cap rate, and how long it takes.

Where Toronto allows them.

  • Fourplexes: up to four units on any residential lot in the city, as-of-right since May 2023.
  • Fiveplexes and sixplexes: in the Toronto and East York wards 4, 9, 10, 11, 12, 13, 14 and 19, and in Ward 23 Scarborough North (2025).
  • Built form: since 2025, multiplexes get 45% lot coverage and no floor space index cap where the zone allowed less. Height, setbacks and building depth still apply.
  • Parking: no minimum for most homes since 2022.
  • Garden and laneway suites: can often be added on the same lot.

Development charges.

Toronto doesn’t charge its development charges or parkland fees on multiplexes of up to six units. Fourplexes were exempted first, and council extended the exemption to five- and six-unit buildings in 2025. Some other charges may still apply, so we confirm them for each project.

Building Code basics.

Most multiplexes are designed under Part 9 of the Ontario Building Code: up to three storeys and a 600 m² footprint. Every unit needs fire separations, and some layouts need sprinklers or extra exits. These choices change the plan and the budget, so we settle them at the concept stage.

What it costs.

We price multiplex construction at $285 to $375 per square foot of above-grade floor area, including stairs, walls and common areas (about 12% on top of the units). A basement apartment adds 75% of that rate for its floor area. Typical all-in budgets, including design, permits, contingency, demolition and services, before land and HST:

BuildingAbove gradeAll-in budget
Fourplex, 4 × 850 sq ft units3,800 sq ft$1.27M–$1.79M
Sixplex, 6 × 850 sq ft units5,700 sq ft$1.88M–$2.63M

The numbers: a 6% cap rate.

Every budget we put in front of an investor is set to clear a 6% cap rate on all-in cost: net operating income divided by the lot, construction, design, permits, fees, financing and contingency.

On our investor calculator, a sixplex with $3,300 average rents, 850 sq ft units, construction at $300 per square foot and a $900,000 lot shows about 6.9%. The same inputs for a fourplex show about 6.0%, just under the line, which is why lot price and unit count matter so much.

Calculator assumptions: 12% added for common areas, design, permits and fees at 8% and financing and contingency at 5% of construction, 3% vacancy, operating costs at 15% of rent, all before HST. Rents and costs are estimates; the return itself can’t be guaranteed.

The timeline.

StageTypical time
Lot test and Lot Check1 to 4 weeks
Design and pricing3 to 5 months
Building permit2 to 4 months
ConstructionAbout 11 to 14 months

Start to finish, plan on about 16 to 23 months. A variance adds three to six months.

Financing and incentives.

  • CMHC MLI Select can offer better financing terms for rental buildings of five units or more that meet affordability, energy or accessibility targets.
  • GST/HST rental rebates can apply to new purpose-built rental buildings with at least four units, if nearly all units are rented long-term.
  • Ontario’s 2026 HST relief includes qualifying new rental properties; see our HST relief guide.

Each program has its own rules and deadlines. Check eligibility with your accountant and lender before you count on them.

General information, current to November 4, 2026. Rules and programs change; check the details for your property before you rely on them.

Questions

Quick answers.

Ask a question
Can I live in one of the units?

Yes. Many owners live in one unit and rent the rest. Some rental rebates require nearly all units to be rented long-term, so check before you decide.

Fourplex or sixplex?

A sixplex spreads the lot cost over more units, so it often clears 6% where a fourplex doesn’t. It’s only allowed in certain wards, and it needs more careful fire and exit design.

Do I need a variance?

Not if the design meets the multiplex standards. Many fourplexes go straight to a building permit. We test the lot before design so you know early.

Free Lot Check

What applies to your lot?

Send the address. Within two business days you get the zoning, what you can build, the approvals you’d need, a budget range and a timeline.

  • Free and no obligation
  • Reviewed by Sami personally
  • Then, if you like, a site walk

Request your free Lot Check.

Send the address and a line about your plans. Sami reviews every request and sends your one-page Lot Check within two business days. Fields marked * are required.

Your project *

Free and no obligation. See our privacy notice.

Free Lot Check