Timeline

How long does a custom home take in Ontario?

Design and approvals first, then under 12 months from permit to keys. Here’s each stage, what can slow it down and how to keep your schedule.

The short answer.

For a typical GTA custom home that fits the zoning, plan on about 14 to 20 months from your first meeting to keys: 3 to 5 months of design, 1 to 3 months for the building permit, and under 12 months of construction. A minor variance adds about 3 to 6 months. A rezoning adds a year or more.

Stage by stage.

StageTypical timeWhat happens
Lot Check and feasibility1 to 4 weeksZoning, what fits, a budget range and a timeline
Survey and reports2 to 6 weeksTopographic survey; arborist or geotechnical reports where needed
Design and pricing2 to 4 monthsConcept, 3D views, line-by-line proposal, permit drawings
Committee of Adjustment3 to 6 months, only if neededNotice, hearing, decision and the 20-day appeal period
Building permit1 to 3 monthsPlans review, revisions and the permit
ConstructionUnder 12 monthsPermit to keys

The 12-month build, month by month.

  • Month 0. Building permit issued.
  • Month 2. Foundation complete.
  • Month 5. Roof on, windows in.
  • Month 7. Drywall complete.
  • Month 10. Kitchen and finishes in.
  • Before month 12. Keys in hand.

That’s the schedule every Oaksmith home runs on. It holds because design, pricing and selections are settled before the clock starts.

Why permits take as long as they do.

Ontario’s Building Code gives municipalities 10 business days to decide on a complete permit application for a house. In practice the clock restarts when an application is incomplete or the zoning review finds a problem, which is why permits often take one to three months.

Recent provincial changes help. Most residential projects of 10 units or fewer no longer need site plan approval, and since 2025 setbacks can be up to 10% smaller than the zoning by-law requires without a minor variance on most urban lots.

What slows custom homes down.

  • Late decisions and changes. The most common cause of delay on any custom home.
  • Long-lead materials. Windows, custom millwork and some finishes take weeks or months to arrive.
  • Utilities. Disconnections before demolition and new connections can take weeks.
  • Variances. A Committee of Adjustment hearing adds months. Since 2022, neighbours can no longer appeal minor variances to the Ontario Land Tribunal, so appeals are rarer.
  • Winter. Foundations can be poured in winter with heating and protection, at extra cost.

How we keep it under 12 months.

  • Design and selections are settled before construction starts.
  • Long-lead items are ordered early.
  • Trades are booked ahead and inspections requested in advance.
  • Sami walks the site every week and sends you photo updates.

General information, current to November 4, 2026. Rules and programs change; check the details for your property before you rely on them.

Questions

Quick answers.

Ask a question
When should I start design for a spring start?

Usually the fall before. Three to five months of design plus one to three months for the permit puts a November start on track for spring, if no variance is needed.

Does the 12 months include the basement and finishes?

Yes. Our under-12-months promise runs from the day the building permit is issued to the day you get your keys, for the whole house.

Can construction start in winter?

Yes. Excavation and foundations can go ahead in winter with ground heaters and insulated blankets. It costs more, but it can save months.

Free Lot Check

What applies to your lot?

Send the address. Within two business days you get the zoning, what you can build, the approvals you’d need, a budget range and a timeline.

  • Free and no obligation
  • Reviewed by Sami personally
  • Then, if you like, a site walk

Request your free Lot Check.

Send the address and a line about your plans. Sami reviews every request and sends your one-page Lot Check within two business days. Fields marked * are required.

Your project *

Free and no obligation. See our privacy notice.

Free Lot Check